The mountain
REDDAP in Ramme, Denmark, is the world’s first dynamic Power-to-Ammonia plant: a 10 MW facility whose electrical load follows wind and solar generation. Shortly before energization, the grid-connection process asked for a complete set of detailed models and data for the rectifier system: harmonic emissions, frequency-dependent impedances, equivalent circuits, protection and control behaviour, and RMS and EMT models. Taken as one block, it meant a development programme far longer than the plant’s schedule allowed. It looked impossible.
Untangling it
I didn’t attack the mountain. I took it apart. Instead of one all-or-nothing task, I asked three simple questions: What does the grid operator really need in order to decide? What applies to this specific plant? What can we answer with what we already have? The answers turned one overwhelming request into nine clear work packages, each small enough to solve and to explain.
I led a small team of internal and external experts through them one by one, and acted as the single technical interface for the customer, its grid consultant, the grid operator and several ABB organizations. Every piece was closed with a plain-language explanation that anyone, technical or not, could follow.
The result
In October 2025 the grid operator accepted the package with no remaining technical open points. In December 2025 the plant delivered its first green ammonia. The harmonic model later supported a published academic study on harmonic-compliance assessment of hybrid power plants.
The method I bring
- Break it down: complex problems rarely need one big answer; they need the right small questions.
- Understand it deeply: deeply enough to explain every piece to anyone, from specialist to decision maker.
- Own it: stay accountable until the last piece is solved.
The mountain
REDDAP is a pioneering project in Denmark that uses wind and solar electricity to produce green hydrogen and ammonia. ABB supplied key technology, including the rectifier systems that feed the electrolyzers. As the plant approached operation, the grid-approval process asked for technical models and data that were not part of any standard delivery: broad, highly specialized and, at first sight, requiring detailed digital models of the rectifier product. Developed literally, that would have taken far longer than the plant could wait. The start-up schedule was at risk.
Step 1 · Find the real question
The first instinct with a request like this is to start building models. I started by asking what the decision actually was. Direct technical discussions with the grid operator separated the requirements written for power-generating plants from those that apply to an industrial consumer, and showed that harmonic behaviour was what mattered most for this installation. One clarification removed a large part of the mountain before a single calculation was made.
Step 2 · Break it into pieces
I split what remained into nine independent work packages, each with one clear question:
- regulatory applicability;
- harmonic emissions;
- equivalent impedance;
- meaningful operating points;
- interharmonics;
- 6-pulse, 12-pulse and idle operation;
- protection and control;
- documentation and traceability;
- closing the authority’s comments.
Each package could then be solved with the best tool for that piece: an analytical calculation, a focused simulation, existing product knowledge or a clear technical explanation, instead of one universal model that did not yet exist.
Step 3 · Solve each piece, and make it understandable
I led a small team of internal and external experts through the packages, reviewed every result and wrote the explanation that went with it. Each deliverable stated what had been calculated, from which point of view, under which assumptions, and where its limits were. That clarity mattered as much as the numbers: the customer, its consultant and the authority could all follow the reasoning, so every piece that was delivered stayed closed.
Step 4 · One interface, all the way to the end
The case involved the customer, its grid consultant, the grid operator, ABB Denmark, ABB’s hydrogen organization and the product specialists. I acted as the single technical interface: following every question through several review cycles, turning every comment into an engineering action and every result into an explanation each audience could use, until nothing was left open.
The outcome
In October 2025 the customer confirmed that the grid operator had accepted the deliverables, with no remaining technical open points on the harmonic and model topics. The plant entered operation and delivered its first green ammonia in December 2025, and the customer expressed its appreciation for the support that helped reach this milestone. The harmonic model later supported an academic framework for harmonic-compliance assessment of complex hybrid power plants.
Value created
- Schedule protection: the customer moved forward without waiting for a long-term model-development programme.
- Regulatory progress: every technical open point accepted by the grid operator.
- Customer trust: a critical escalation turned into positive customer feedback.
- Risk reduction: a defensible solution without unnecessary exposure of confidential product details.
- Reusable learning: a method and results that became a reference for later harmonic and grid-integration studies.
The method I bring
Complex problems rarely need one big answer. They need someone who understands them deeply enough to find the right small questions, solve them one by one and explain every answer to anyone. That is how I approach every challenge, and how I lead: by example, working through the detail myself, so that everyone involved knows where we are going and why.
The mountain
REDDAP is a 10 MW dynamic Power-to-Ammonia facility in Denmark that combines renewable generation, electrolysis, rectifier systems and ammonia synthesis. Its operating principle requires the electrical load to follow variable wind and solar generation, which makes it an unusual grid-integration case with evolving simulation requirements.
To support the plant-level model submitted to the grid operator, Energinet, the customer needed technical information for the rectifier branch covering:
- harmonic and interharmonic emissions;
- frequency-dependent equivalent impedance;
- Norton or Thevenin representation of the rectifier branch;
- operation at different load levels;
- protection functions and trip behaviour;
- simplified control-loop and transfer-function representation;
- RMS and EMT modelling expectations;
- documentation and eventual model verification.
A full future-state answer could have meant RMS models down to the control loops, EMT models down to switching level, verification documentation and possibly hardware-in-the-loop or site validation. The immediate priority was narrower: reliable, explainable information that allowed the authority to assess the actual grid risk of the installed 12-pulse thyristor rectifier system. The task was therefore to separate three things:
- what a fully reusable product model might eventually require;
- what was relevant to the specific REDDAP configuration;
- what was actually needed to close the authority’s immediate technical comments.
The method: nine work packages
No single existing model or standard deliverable addressed the full request, so I took end-to-end responsibility and split it into independent workstreams, each solved with the most suitable mix of analytical calculation, simulation, product knowledge, factory information and engineering judgement:
- clarification of regulatory applicability;
- harmonic-emission calculation;
- equivalent-impedance derivation;
- definition of meaningful operating points;
- assessment of interharmonics;
- clarification of 6-pulse, 12-pulse and idle operation;
- protection and control representation;
- documentation and traceability;
- direct resolution of the authority’s comments.
Piece by piece · Clarifying the real requirement
A major part of the work was separating requirements written for power-generating or actively controlled converter systems from those applicable to a rectifier load. Discussions with the grid operator confirmed that consuming facilities can be treated differently, that requirements scale with plant size and grid relevance, and that harmonic behaviour was the key concern for this installation. The task changed from reproducing every internal control detail to providing what was needed to assess harmonic emissions, network interaction, frequency-domain behaviour, protection and operating assumptions, and overall grid risk.
Piece by piece · The harmonic representation
The installed system consists of two 6-pulse bridges operating together as a 12-pulse rectifier, so the submission represented the complete electrolysis branch as seen from the grid, not an isolated semiconductor bridge. The package included:
- harmonic currents at the medium-voltage side, including transformer and branch effects;
- operating points at 15 %, 50 %, 75 % and 100 % load;
- phase-specific current and voltage information;
- equivalent impedance for all three phases (resistance and reactance);
- DFT/FFT-based processing of voltage and current;
- 1 Hz resolution datasets for direct integration into the plant model;
- explanations for frequencies where calculated values carry little physical meaning.
Piece by piece · The complex-impedance question
One of the hardest points was the sign and physical meaning of the calculated complex impedance. At the fundamental frequency, active power flows from the network to the rectifier load; at characteristic harmonic frequencies, the harmonic currents generated by the rectifier flow in the opposite direction, towards the network. This change of reference direction affects the signs of the voltage-to-current ratio. The analysis showed that:
- the system is inductive at the fundamental frequency;
- characteristic harmonics are injected towards the supply network;
- voltage and current harmonic directions must be interpreted consistently;
- where harmonic voltage or current is negligible, the calculated ratio can be numerically valid but physically meaningless;
- impedance data must therefore be read together with the harmonic voltage and current datasets, not as an isolated table.
Analytical calculation and Simulink simulation were compared, and the conversion method was documented so that the customer and authority could trace every step.
Piece by piece · Operating cases that did not apply
6-pulse operation: the two bridges form one 12-pulse system; if one stops or trips, the other stops too, so sustained 6-pulse operation is not a normal operating point. Idle operation: at zero output the thyristor firing pulses are blocked and no active power flows, unlike an active-front-end converter that can still exchange reactive power. Below 15 % load: treated as a transient region rather than a stable harmonic operating point. The model scope therefore followed the real behaviour of the system instead of filling a generic template with misleading cases.
Holding the pieces together
The solution required coordination between the customer and plant owner, the plant-level electrical consultant, the grid operator, ABB Denmark, ABB’s hydrogen organization, rectifier product and engineering specialists, and a small team of internal and external experts that I led on the analytical and simulation work. I prepared consolidated question lists, translated broad requirements into individual engineering actions, reviewed the calculations and wrote the customer explanations through several review cycles. Every deliverable stated what had been calculated, from which electrical reference point, under which assumptions and operating configurations, how the conversion was performed, and where the limits of interpretation were.
Result
In October 2025 the grid operator accepted the submitted deliverables, with no remaining technical open points on the harmonic and model topics, clearing the way for plant testing and approval. REDDAP entered operation and delivered its first green ammonia in December 2025. The harmonic model later supported an academic harmonic-compliance framework, which reported close agreement between original and recreated plant models in the principal harmonic, load-flow, distortion and impedance results.
Why the method worked
- clarifying the actual regulatory decision criteria;
- separating immediate project needs from future product development;
- decomposing an unclear request into manageable work packages;
- using analytical calculations and targeted simulations where full models were unavailable;
- documenting assumptions and limitations transparently;
- keeping direct communication between all technical stakeholders;
- remaining accountable until the authority’s final comments were closed.